EAC Formula: How to Calculate Estimate at Completion (4 Ways)

The EAC formula calculates Estimate at Completion, the total a project will cost when it is finished. The basic formula is EAC = AC + ETC: actual cost so far plus the estimated cost of the remaining work. The most used version is EAC = BAC / CPI, which assumes cost performance to date continues.

By Morten Fabrin, CEO of SUNAGO Matrix Updated 12 min read

A project in SUNAGO Matrix: progress in hours, budget used, and forecast profit and margin

There are four standard ways to calculate EAC, and on the same project they can give answers tens of thousands of dollars apart. This guide shows all four with one worked example, explains how EAC relates to ETC, BAC and VAC, tells you which formula fits which situation, and covers what changes when your costs are hours, as in consulting and time-and-materials work. At the end there is a short section on FAC (Forecast at Completion).

The 4 EAC formulas at a glance

#FormulaAssumesUse it when
1EAC = BAC / CPICost performance so far continues to the endThe overrun or underrun is a trend, not an accident. This is the default.
2EAC = AC + ETC (bottom-up)The remaining work is re-estimated from scratchThe original plan is no longer valid: scope changed, the team changed or the estimate was wrong.
3EAC = AC + (BAC - EV)Past variance was a one-off; the rest goes to planA single event caused the variance, and you have evidence it will not repeat.
4EAC = AC + (BAC - EV) / (CPI x SPI)Both cost and schedule performance affect the restYou are behind schedule and must catch up, which usually costs extra. Gives the most pessimistic forecast when both indices are below 1.

Formula 1 is often also written as EAC = AC + (BAC - EV) / CPI. It is the same formula: both give the same number, because the remaining work (BAC - EV) is simply priced at the current cost efficiency. The SAS earned value documentation defines the estimate to complete in exactly these forms: the remaining work, the remaining work divided by CPI, and the remaining work divided by CPI x SPI.

The inputs: BAC, AC, EV, PV, CPI and SPI

Every EAC formula is built from the same few numbers, all measured at the same date.

BAC  Budget at Completion   the approved total budget
PV   Planned Value          budget value of the work that should be done by now
EV   Earned Value           budget value of the work actually done (% complete x BAC)
AC   Actual Cost            what the work done so far has actually cost

CPI  = EV / AC              cost performance index (below 1 = over budget)
SPI  = EV / PV              schedule performance index (below 1 = behind schedule)

Earned value is the key. Spending 50% of the budget says nothing on its own. Spending 50% of the budget while finishing 40% of the work says you are getting 80 cents of work for every dollar, and that is what CPI measures.

ETC vs EAC vs BAC vs VAC

These four terms are easy to mix up. The difference is what each one measures and when it changes.

TermStands forWhat it tells youFormulaChanges over time?
BACBudget at CompletionThe approved budget for the whole projectSet at the startOnly by a formal change
EACEstimate at CompletionThe forecast total cost of the whole projectAC + ETCYes, at every update
ETCEstimate to CompleteThe forecast cost of the work still leftEAC - ACYes
VACVariance at CompletionThe forecast overrun or underrun at the endBAC - EACYes. Negative = over budget
TCPITo-Complete Performance IndexThe cost efficiency you need from now on to still hit the budget(BAC - EV) / (BAC - AC)Yes. Above 1 = you must do better than plan

Worked example: one project, four EACs

A consulting firm runs a fixed-fee process redesign project. The cost budget is $200,000. At the halfway review the numbers are:

  • BAC = $200,000
  • PV = $100,000 (the plan said 50% done by now)
  • EV = $80,000 (the work is 40% done: 40% x $200,000)
  • AC = $100,000 (cost of the hours and expenses so far)

That gives:

  • CPI = EV / AC = 80,000 / 100,000 = 0.80. Each dollar buys 80 cents of planned work.
  • SPI = EV / PV = 80,000 / 100,000 = 0.80. The project is 20% behind schedule.

Now the four EACs:

Formula 1, EAC = BAC / CPI
200,000 / 0.80 = $250,000

Formula 2, EAC = AC + bottom-up ETC. The team re-estimates the remaining tasks at 1,100 hours at an average cost of $120 per hour, so ETC = $132,000.
100,000 + 132,000 = $232,000

Formula 3, EAC = AC + (BAC - EV)
100,000 + (200,000 - 80,000) = 100,000 + 120,000 = $220,000

Formula 4, EAC = AC + (BAC - EV) / (CPI x SPI)
CPI x SPI = 0.80 x 0.80 = 0.64
100,000 + 120,000 / 0.64 = 100,000 + 187,500 = $287,500

FormulaEACETC (EAC - AC)VAC (BAC - EAC)
1. BAC / CPI$250,000$150,000-$50,000
2. AC + bottom-up ETC$232,000$132,000-$32,000
3. AC + (BAC - EV)$220,000$120,000-$20,000
4. AC + (BAC - EV) / (CPI x SPI)$287,500$187,500-$87,500

And the TCPI = (200,000 - 80,000) / (200,000 - 100,000) = 120,000 / 100,000 = 1.20. To still finish on budget, every remaining dollar has to buy 20% more work than planned, while the team has so far delivered 20% less. That gap is the honest answer to "can we still make the budget?". Usually the answer is no, and the conversation should be about scope, fee or schedule instead.

The spread between $220,000 and $287,500 is not a flaw in the formulas. Each answers a different question, which is why choosing the formula is a judgement call.

Want to skip the arithmetic? The calculator below runs all four formulas on your own numbers.

EAC Calculator: All Four Formulas at Once

The four EAC formulas give different answers for the same project on the same day. Most calculators show one number and leave you to assume there is only one. This one runs all four on your figures, shows the gap between the highest and the lowest, and says what each formula assumes about the work that is left.

The approved budget for the whole project.

What has actually been spent so far. Enter 0 if nothing has been spent yet.

Progress - enter one of the two *

Earned value is calculated as BAC × percent complete.

The budget value of the work actually finished. Used instead of percent complete.

Planned value is the value the plan said would have been delivered by this point. It is what makes SPI possible: SPI = EV / PV. Leave it empty and formula 4 is shown as unavailable, with the reason.

The delivery team's own re-estimate of the cost of the remaining work. Enables formula 2.

The spread between the formulas

$67,500

Lowest $220,000 (EAC = AC + (BAC − EV)) · highest $287,500 (EAC = AC + (BAC − EV) / (CPI × SPI))

Same project, same day, same numbers: $67,500 between the highest and the lowest forecast, depending only on which formula you pick. The gap is the decision you actually have to make - was the variance a one-off, or is it how this project runs?

EAC = BAC / CPI

$250,000

EAC = BAC × AC / EV = $200,000 × $100,000 / $80,000 = $250,000

Algebraically identical to BAC / CPI, but with no divisor to round. CPI here is 0.800000; dividing by a rounded CPI gives a different answer at every number of digits.

Used when

The variance so far continues for the rest of the project

ETC $150,000 · VAC -$50,000

EAC = AC + bottom-up ETC

$232,000

EAC = AC + ETC = $100,000 + $132,000 = $232,000

Used when

The original estimate no longer holds, so the team re-estimates the remaining work

ETC $132,000 · VAC -$32,000

EAC = AC + (BAC − EV)

$220,000

EAC = AC + (BAC − EV) = $100,000 + ($200,000 − $80,000) = $220,000

Used when

The variance was a one-off; the remaining work runs to budget

ETC $120,000 · VAC -$20,000

EAC = AC + (BAC − EV) / (CPI × SPI)

$287,500

EAC = AC + (BAC − EV) / (CPI × SPI) = $100,000 + ($200,000 − $80,000) / (0.800000 × 0.800000) = $287,500

Used when

Both cost and schedule performance carry into the remaining work

ETC $187,500 · VAC -$87,500

The indices behind the forecasts

EV - Earned value

$80,000

40% × $200,000

CPI - Cost performance index

0.800000

$80,000 / $100,000

SPI - Schedule performance index

0.800000

$80,000 / $100,000

TCPI to BAC

The efficiency the remaining work needs to still land on the original budget

1.2000

($200,000 − $80,000) / ($200,000 − $100,000)

TCPI to EAC

The efficiency the remaining work needs to land on your new forecast

0.8000

($200,000 − $80,000) / ($250,000 − $100,000), using EAC = BAC / CPI

Want this calculated automatically on every project, from the hours your team logs? See what SUNAGO Matrix costs.

Which EAC formula should you use?

Ask these questions in order:

  1. Is the original plan still valid? If not (scope changed, key people left, the estimate was clearly wrong), use formula 2 and re-estimate the remaining work bottom-up. A formula cannot fix a plan that no longer describes the work.
  2. Was the variance caused by a single event that will not repeat? For example a one-time rework or a licence bought twice. Then formula 3 is fair. Be strict: "it will get better" is not evidence.
  3. Is the project behind schedule with a fixed deadline you must still meet? Catching up costs overtime, extra people or faster but pricier resources. Formula 4 reflects that.
  4. None of the above? Use formula 1. Once a project is underway, cost performance rarely improves by itself, so BAC / CPI is the sensible default.

Two practical tips:

  • Calculate more than one. Reporting formula 1 and formula 4 side by side gives a realistic range, and a big gap between them is a warning in itself.
  • Do not trust CPI too early. In the first weeks a few entries can swing CPI a lot. Use a bottom-up ETC until there is enough progress for the trend to mean something.

How to calculate EAC in Excel or Google Sheets

Put the inputs in column B:

CellValue
B1BAC
B2EV
B3AC
B4PV
B5Bottom-up ETC

Then:

CPI                         =B2/B3
SPI                         =B2/B4
EAC 1  BAC / CPI            =B1*B3/B2
EAC 2  AC + ETC             =B3+B5
EAC 3  AC + (BAC - EV)      =B3+(B1-B2)
EAC 4  CPI x SPI version    =B3+(B1-B2)/((B2/B3)*(B2/B4))
VAC                         =B1-[EAC cell]
TCPI                        =(B1-B2)/(B1-B3)

Formula 1 is written as BAC x AC / EV on purpose. It is the same as BAC / CPI, but it never divides by a rounded CPI. When CPI is a recurring decimal such as 0.8181..., rounding it to 0.82 before dividing shifts the EAC by hundreds or thousands of dollars on a large budget.

EAC for consulting and time-and-materials projects

Textbook EAC examples tend to come from construction or IT projects with materials and equipment. In a consulting, engineering or agency project, almost all of the cost is people's time. That changes where the numbers come from.

Hours are the actual cost

On a services project, AC = hours logged x the cost price per hour of each person, plus any expenses. The cost price per hour is not the salary divided by 1,800. It includes the firm's overhead spread over the billable hours, which is why many firms work it out once with a tool like the cost per billable hour calculator.

Because AC comes from hours, the timesheet is the input to your EAC. If the timesheet is late or incomplete, the EAC is wrong in a predictable direction: missing hours make AC too low, CPI too high and the EAC too optimistic. Two weeks of hours that nobody has entered yet can hide exactly the overrun you are trying to see.

Calculate EAC in hours first

For services work it often helps to run the formula in hours and convert to money afterwards:

  • Hour budget: 1,000 hours
  • Hours logged: 600
  • Work completed: 50%, so earned hours = 500
  • Hour CPI = 500 / 600 = 0.833...
  • EAC in hours = 1,000 x 600 / 500 = 1,200 hours

Then convert: multiply by cost prices for the cost EAC, and by bill rates for the revenue forecast. If the staffing mix shifts, for example a senior takes over from a junior, use each person's own cost price rather than a blended average, or the cost EAC drifts away from reality.

Fixed fee vs time and materials

  • Fixed fee: revenue is locked, so every dollar of overrun comes straight out of your margin. EAC is a margin forecast in disguise, and the project profitability tracking view is where it pays off.
  • Time and materials: extra hours are usually billable, so an overrun does not hit your margin directly. EAC still matters for two reasons. First, the client has a budget, and an EAC above it is a conversation you want to have early. Second, many T&M contracts have a cap or not-to-exceed amount. In the example above, a cap of 1,000 hours means 200 forecast hours will either be unbillable or need a change order.
  • Retainers and capped contracts behave like fixed fee once the included hours or the cap are used up.

Keep EAC current

A weekly EAC built on approved timesheets catches drift while there is still time to act. A monthly EAC built on last month's spreadsheet export usually confirms what the team already suspects. Watching utilization rate alongside EAC also shows whether an overrun is caused by too many hours on the project or by the wrong people doing them. Both belong in the short list of KPIs for consulting firms.

What is FAC (Forecast at Completion)?

FAC stands for Forecast at Completion. It is used in two ways:

  1. As another name for EAC. Many organisations, especially in engineering, construction and corporate finance, say FAC for the forecast final cost. In that use, FAC and EAC are the same number.
  2. As the forecast final result. Some consulting and engineering firms use FAC for the outcome rather than the cost: forecast revenue minus EAC, giving the expected margin when the project closes.

Using the worked example: if the fixed fee is $260,000, the planned margin was $60,000 (23.1%). With an EAC of $250,000 (formula 1), the forecast margin is $10,000, or 3.8%. The cost overrun of $50,000 is a margin loss of the same size.

Neither use is wrong, but mixing them in one report is. Decide which definition your firm uses and write it next to the number.

EAC in finance and accounting

Two other meanings show up when people search for "EAC finance" or "EAC accounting":

  • Equivalent Annual Cost. In capital budgeting, EAC is the yearly cost of owning an asset over its life, used to compare assets with different lifespans. A common form is EAC = (asset price x discount rate) / (1 - (1 + discount rate)^-n), plus yearly running costs. It has nothing to do with project forecasting.
  • Estimate at Completion in revenue recognition. Firms that recognise revenue over time with a cost-to-cost method measure progress as cost incurred divided by the estimated total cost. That estimated total cost is the EAC, so a change in EAC changes how much revenue is recognised, and a forecast loss on a contract may need to be recognised early. Your accountant or auditor sets the rules here.

How SUNAGO Matrix helps with the forecast

SUNAGO Matrix connects the timesheet to the project budget, so the actual cost behind your EAC is not a monthly export.

  • Timesheet is free for everyone in the firm, with approvals and locked periods. Outlook meetings and Activity Logger, a Windows program, suggest the time, and employees approve it, so fewer hours go missing.
  • With Project management (EUR 9.99 per user with access per month), each project has a time budget with warnings at the limits you choose and the date the budget runs out at today's pace. Tasks show their estimate against the time spent and what is left, which is the raw material for a bottom-up ETC.
  • With Costs and rates (a company-wide upgrade at EUR 1 a month), registered hours become costs at the cost price of the day. Together with Project management, each project shows a forecast of the final result and the margin, for fixed price or time and materials, with each number explained. The cost price is saved on every time entry, so it stays fixed when a salary changes, unless an admin chooses Recalculate.
  • With Project management and Allocation and Resources, the project's Timeline can show Ahead or behind: Schedule performance and Budget performance for each project, week by week, where 1.00 is on plan and on budget. Schedule performance is work done divided by work planned by then, and Budget performance is work done divided by what it cost, the same ratios as the indices above.

Summary

  • EAC = AC + ETC is the definition. EAC = BAC / CPI is the default formula.
  • Use AC + (BAC - EV) only for a proven one-off variance, AC + (BAC - EV) / (CPI x SPI) when a schedule catch-up will cost extra, and a bottom-up ETC when the plan no longer fits the work.
  • ETC is what is left, EAC the total, BAC the plan, VAC the gap, and TCPI the efficiency you would need to hit the budget.
  • On services projects, hours are the actual cost, so timesheets are the input to EAC. Late hours make the forecast look better than it is.
  • FAC means either the same as EAC or the forecast final margin. Pick one meaning and stick to it.

Start free with Timesheet and get the hours behind your EAC in on time. Try Project management and Costs and rates free for 7 days when you want the forecast and margin on every project.

Frequently Asked Questions About EAC and FAC

Common questions about Estimate at Completion and Forecast at Completion in consulting project management.

What is EAC in project management?

EAC (Estimate at Completion) is the forecast of what a project will cost in total when it is finished. It equals the actual cost spent so far plus the estimated cost of the remaining work. Unlike the budget (BAC), EAC changes every time you measure progress, so it shows early whether a project is heading for an overrun.

What does EAC stand for?

In project management, EAC stands for Estimate at Completion: the forecast total cost of a project. In finance and capital budgeting, EAC usually means Equivalent Annual Cost, the yearly cost of owning an asset over its life. The two are unrelated, so check the context. If the formula contains BAC, CPI or earned value, it is Estimate at Completion.

What is the difference between ETC and EAC?

ETC (Estimate to Complete) is the cost of the work that is still left. EAC (Estimate at Completion) is the total cost of the whole project: what you have already spent plus the ETC. So EAC = AC + ETC, and ETC = EAC - AC. If you have spent $100,000 and $150,000 of work remains, ETC is $150,000 and EAC is $250,000.

Which EAC formula is the most accurate?

No single formula is always most accurate. EAC = BAC / CPI is the most common default because cost performance tends to persist once a project is underway. Use AC + (BAC - EV) only when the variance was a one-off. Use the CPI x SPI version when you must recover a schedule delay. Use a bottom-up ETC when the original plan no longer reflects the work.

What is the difference between EAC and FAC?

FAC (Forecast at Completion) is often used as another name for EAC: the forecast final cost. Some firms, especially in consulting and engineering, use FAC for the forecast final result instead, comparing forecast cost with the contract value to show the expected margin. Agree on one definition inside your firm before comparing projects.

How do I calculate EAC in Excel?

Put BAC, EV and AC in cells B1, B2 and B3, and PV in B4. CPI is =B2/B3 and SPI is =B2/B4. Then EAC = BAC / CPI is =B1*B3/B2, the one-off variance version is =B3+(B1-B2), and the CPI x SPI version is =B3+(B1-B2)/((B2/B3)*(B2/B4)). Keep CPI unrounded in the cell to avoid rounding errors.

Can EAC be lower than the budget?

Yes. When CPI is above 1, the project delivers more work per dollar than planned, and EAC = BAC / CPI comes out below BAC. The variance at completion (VAC = BAC - EAC) is then positive, which means a forecast underrun. On a fixed-price project that underrun becomes extra margin, as long as the quality and scope stay as agreed.

See the Forecast and Margin on Every Project

Stop discovering budget problems at project close. SUNAGO Matrix gives you a forecast, profit and margin on every project, without spreadsheets. Start free with Timesheet, and try Project management and Costs and rates free for 7 days.

Open the live demo

Free. No card needed.