This guide explains both Estimate at Completion (EAC) and Forecast at Completion (FAC) - what they are, how they differ, and how they apply specifically to consulting and engineering firms with 10–50 employees. Not textbook theory. Practical application for firms who can't afford to discover margin problems after the fact.
Every example, every formula, every recommendation here is framed through the lens of professional services delivery - because that's where EAC FAC project management tracking creates the most value. It is one of the ten KPIs a firm this size should run on.
If you came here to run the numbers rather than read about them, the EAC calculator is further down the page: enter your budget, cost to date and progress, and it runs all four EAC formulas at once.
Understanding EAC and FAC for Consulting Firms
Two complementary metrics that give you different but equally essential views of project financial health.
Estimate at Completion (EAC)
EAC predicts total project cost based on actual performance to date plus estimated remaining costs. It's the single most important number for understanding whether a project will finish on budget.
Formula: EAC = Actual Cost + Estimate to Complete
For consulting firms, "actual cost" is primarily hours logged × employee cost rate. Knowing whether your 500-hour engagement will land at 500 or 620 hours - and what that does to margin - is what EAC delivers.
Forecast at Completion (FAC)
While EAC focuses on cost, FAC forecasts total project outcome - incorporating both cost and revenue. It answers: "When this project is done, what will our actual margin be?"
FAC is critical for fixed-price engagements. The fee is locked at signing, but cost drifts with every additional hour.
Think of EAC as the speedometer - how fast costs accumulate. FAC is the fuel gauge - will you make it to profitable delivery or run out before you get there?
The EAC Formulas, and a Worked Example
The definitions above are circular on their own: EAC is actual cost plus what is left to spend, and what is left to spend is EAC minus actual cost. To get from data to a number you need earned value. Three inputs, measured at the same moment:
- BAC - Budget at Completion. The approved budget.
- EV - Earned Value. Budget value of the work actually finished: percent complete × BAC.
- AC - Actual Cost. What has been spent to date.
From those, the standard earned-value formulas:
CPI = EV / AC cost performance index
EAC = BAC / CPI the variance so far continues
= BAC x AC / EV same thing, no rounded divisor
EAC = AC + (BAC - EV) the rest goes to plan
EAC = AC + (BAC - EV) / (CPI x SPI) cost and schedule both slipping
ETC = EAC - AC what is still to spend
VAC = BAC - EAC the overrun, if negative
TCPI = (BAC - EV) / (BAC - AC) efficiency needed to still hit BACWorked example. A fixed-fee engineering study is budgeted at BAC = $400,000. Halfway through the schedule, the team has completed 45% of the work and spent $220,000.
- EV = 45% × $400,000 = $180,000
- AC = $220,000
- CPI = EV / AC = $180,000 / $220,000 = 0.8181... (a recurring decimal - never round it before dividing by it)
You are getting about 82 cents of work for every dollar spent. If that rate continues, EAC = BAC / CPI - but CPI is a recurring decimal here, so use the equivalent form that has no divisor to round: EAC = BAC × AC / EV = $400,000 × $220,000 / $180,000 = $488,888.89. Round CPI first and you get a different answer at every number of digits - $487,805 at 0.82, $488,878 at 0.8182 - which is exactly the trap this form avoids. The project lands about $89,000 over budget. That is VAC = $400,000 − $488,888.89 = −$88,888.89, and it comes straight out of the fee.
If instead you believe the overrun was a one-off and the remainder will run to plan, EAC = $220,000 + ($400,000 − $180,000) = $440,000. The gap between those two EACs - $488.9k against $440k - is the decision you actually have to make: was this a blip, or is it how the project runs?
Either way, ETC = EAC − AC, so between $220,000 and $269,000 remains to be spent. And TCPI = ($400,000 − $180,000) / ($400,000 − $220,000) = $220,000 / $180,000 = 1.2222...: to still finish at budget, every remaining dollar has to buy about 22% more work than every dollar so far. That is the number that tells you whether recovery is realistic or whether the conversation is about scope and fee instead.
EAC Calculator: All Four Formulas at Once
The four EAC formulas give different answers for the same project on the same day. Most calculators show one number and leave you to assume there is only one. This one runs all four on your figures, shows the gap between the highest and the lowest, and says what each formula assumes about the work that is left.
The spread between the formulas
$48,888.89
Lowest $440,000 (EAC = AC + (BAC − EV)) · highest $488,888.89 (EAC = BAC / CPI)
Same project, same day, same numbers: $48,888.89 between the highest and the lowest forecast, depending only on which formula you pick. The gap is the decision you actually have to make - was the variance a one-off, or is it how this project runs?
EAC = BAC / CPI
$488,888.89
EAC = BAC × AC / EV = $400,000 × $220,000 / $180,000 = $488,888.89
Algebraically identical to BAC / CPI, but with no divisor to round. CPI here is 0.818182; dividing by a rounded CPI gives a different answer at every number of digits.
Used when
The variance so far continues for the rest of the project
ETC $268,888.89 · VAC -$88,888.89
EAC = AC + (BAC − EV)
$440,000
EAC = AC + (BAC − EV) = $220,000 + ($400,000 − $180,000) = $440,000
Used when
The variance was a one-off; the remaining work runs to budget
ETC $220,000 · VAC -$40,000
EAC = AC + (BAC − EV) / (CPI × SPI)
Not available for these inputs
Planned value (PV) is not entered, so SPI cannot be calculated. Planned value is what the plan said would be delivered by now; without it there is no schedule performance to apply.
Used when
Both cost and schedule performance carry into the remaining work
EAC = AC + bottom-up ETC
Not available for these inputs
No bottom-up estimate to complete entered. This formula replaces the maths with the delivery team's own re-estimate of the work that is left.
Used when
The original estimate no longer holds, so the team re-estimates the remaining work
The indices behind the forecasts
EV - Earned value
$180,000
45% × $400,000
CPI - Cost performance index
0.818182
$180,000 / $220,000
SPI - Schedule performance index
Planned value (PV) not entered. SPI is earned value divided by the value the plan said would be delivered by now.
TCPI to BAC
The efficiency the remaining work needs to still land on the original budget
1.2222
($400,000 − $180,000) / ($400,000 − $220,000)
TCPI to EAC
The efficiency the remaining work needs to land on your new forecast
0.8182
($400,000 − $180,000) / ($488,888.89 − $220,000), using EAC = BAC / CPI
Want this calculated automatically on every project, from the hours your team logs? See what SUNAGO Matrix costs.
Why EAC and FAC Matter More in Consulting Than Other Industries
Generic guides treat EAC as a formula exercise. In consulting and engineering, it's a survival metric.
Your Product Is Billable Time - Every Hour Counts
Unlike manufacturing where materials cost is known upfront, consulting project costs are driven entirely by people and hours. A single senior engineer spending 20 extra hours can wipe out the margin entirely. EAC tracks this in real time.
Fixed-Price Projects Create Hidden Risk
Many engineering firms operate on fixed-fee contracts. The client pays a set amount regardless of hours. Without FAC monitoring, you don't know you've lost money until the project is closed. Forecast at Completion turns this from a post-mortem into a proactive tool.
Multi-Phase Projects Make Manual Tracking Impossible
Consulting projects usually run in several phases, each with its own budget. Tracking EAC/FAC across all phases with spreadsheets is error-prone and always out of date. By the time you update Phase 2, Phase 4 is already drifting.
Scope Creep Is the Silent Margin Killer
Engineering projects are especially prone to scope changes - additional revisions, expanded analysis, extra client meetings. Each pushes actual cost up without a fee increase. EAC makes scope creep visible before it becomes a write-off.
How to Track EAC and FAC in Your Consulting Firm
Knowing the EAC formula is easy. Building a system that keeps it accurate is where most firms fail. Here's what's required for reliable project budget tracking.
Connect Time Tracking to Project Budgets
If consultants log hours in one system and budgets live in another, your EAC is always stale. Every hour recorded should immediately recalculate EAC.
billable hours trackingSet Budget Baselines at the Phase Level
Don't just set one total project budget. Break it into phases so you can see which phase is drifting. A project on budget overall may hide a phase at 140%.
project profitability trackingMonitor Budget Burn Rate Weekly
EAC should be reviewed weekly, not monthly. By the time a monthly report shows the overrun, weeks of margin recovery time are gone.
utilization rateUse Real Cost Rates - Not Blended Averages
A junior engineer at $95/hour and a senior at $150/hour produce very different EAC calculations. If your staffing mix shifts mid-project, EAC must reflect it.
How SUNAGO Matrix Forecasts Project Cost and Margin
SUNAGO Matrix removes the spreadsheet layer between time and project money. With Project management and Costs and rates, every project shows a forecast, profit and margin, built from the hours people log in Timesheet and the cost price of each hour.
As an ERP for consulting firms, Matrix integrates project management with financial tracking. With Allocation and Resources you see who is booked and who is free, so you can act when a forecast drifts.
- Logged hours become costs in the project forecast at the cost price of the day, so the forecast follows the time
- Hour budgets with a warning at the limits you choose, and the date the budget runs out at today's pace
- A margin target in percent colours the result green, yellow or red, and each number is explained
- The cost price per hour comes from Costs and rates: salary divided by billable hours plus a share of the firm's expenses, spread per billable hour, per paid hour or equally, as you choose
- Forecast, profit and margin on every project, against the contract (fixed price, time and material or recurring)
- Timesheet, Project management, Costs and rates and CRM share the same data, so nothing is copied between tools
EAC vs. FAC vs. BAC - Quick Reference
Five key metrics every consulting firm should understand for effective earned value management.
BAC (Budget at Completion)
The original approved project budget. Set once at project start.
Static - it doesn't change unless the contract is formally amended.
EAC (Estimate at Completion)
The forecasted total cost based on actual performance to date.
Dynamic - updates as work is performed and hours are logged.
FAC (Forecast at Completion)
The projected final margin/outcome considering both cost and revenue.
Dynamic - tells you if you'll make money. For fixed-price projects, the number that matters most.
ETC (Estimate to Complete)
The remaining cost from today until project end.
Calculated as ETC = EAC − Actual Cost. Shows how much budget is left.
VAC (Variance at Completion)
The difference between BAC and EAC.
Positive = under budget. Negative = over budget. Negative VAC on fixed-price = direct margin loss.