The three numbers behind every EVM formula
Most guides to earned value management are written for defense programs and PMP exam candidates. This one is for the project manager or owner of a consulting, engineering or creative firm who bills time, runs projects of a few hundred hours and wants to know on week 6, not week 12, that a project is heading for a loss. You get every formula in one table, a worked example with real numbers, the methods for measuring percent complete on time-and-materials and fixed-fee work, and an honest list of where EVM breaks down in a small firm.
Everything in earned value management comes from three values, all measured in the same unit (usually money at cost, sometimes hours) and all cumulative to the same date.
| Term | Also called | What it answers | How you get it |
|---|---|---|---|
| Planned value (PV) | BCWS, budgeted cost of work scheduled | How much work should be done by now, in budget terms? | Your time-phased budget: the share of the budget scheduled up to today |
| Earned value (EV) | BCWP, budgeted cost of work performed | How much work is actually done, in budget terms? | Percent complete × budget at completion (BAC) |
| Actual cost (AC) | ACWP, actual cost of work performed | What did the work done so far actually cost? | Approved timesheet hours × each person's cost rate, plus expenses and subcontractors |
One more input sits above all three: budget at completion (BAC), the total planned budget for the project. For a service firm that is normally the internal cost budget, not the fee you charge the client.
The key idea is that EV and PV are both expressed in *budget* terms. That lets you compare progress (EV) with plan (PV) and with spend (AC) on the same scale, which percent-of-budget-spent reports cannot do.
EVM formulas: all eight in one table
These are the standard formulas defined in PMI's Standard for Earned Value Management (ANSI/PMI 19-006-2019), which builds on PMI's earlier *Practice Standard for Earned Value Management*.
| Metric | Formula | What it tells you | Good sign |
|---|---|---|---|
| Cost variance (CV) | CV = EV - AC | Money over or under budget for the work done | Positive |
| Schedule variance (SV) | SV = EV - PV | Work ahead of or behind plan, in budget terms | Positive |
| Cost performance index (CPI) | CPI = EV / AC | Budget value earned per unit of cost spent | 1.0 or above |
| Schedule performance index (SPI) | SPI = EV / PV | Rate of progress against plan | 1.0 or above |
| Estimate at completion (EAC) | EAC = BAC / CPI (typical) or EAC = AC + (BAC - EV) (atypical) or EAC = AC + (BAC - EV) / (CPI × SPI) | Forecast total cost when the project is done | At or below BAC |
| Estimate to complete (ETC) | ETC = EAC - AC | Cost still to spend from today | At or below BAC - EV |
| Variance at completion (VAC) | VAC = BAC - EAC | Forecast overrun (negative) or underrun at the end | Zero or positive |
| To-complete performance index (TCPI) | TCPI = (BAC - EV) / (BAC - AC), or (BAC - EV) / (EAC - AC) against a new target | CPI you need on the remaining work to land on budget | 1.0 or below, and close to the current CPI |
Which EAC to use is a judgment call. BAC / CPI assumes the cost efficiency so far will continue. AC + (BAC - EV) assumes the overrun was a one-off and the rest goes to plan. The CPI × SPI version assumes both cost and schedule pressure carry on, which suits fixed-deadline work where you will add people to catch up. For a full comparison of the variants and when each one fits, see our guide to the EAC formula.
Earned value example: a 400-hour consulting project at week 6
Here is a realistic small-firm project with numbers taken through every formula.
The setup. A five-person consulting team runs an operations review for a client. The fee is fixed at $56,000. The plan is 400 hours over 10 weeks at a blended cost rate of $100 per hour, so:
- BAC = 400 hours × $100 = $40,000 (internal cost budget)
- Planned margin = $56,000 - $40,000 = $16,000, or 28.6% of the fee
The plan spreads the hours evenly at 40 hours a week, and the work is split into five milestones with weights based on their share of the budget:
| Milestone | Weight | Status at end of week 6 |
|---|---|---|
| 1. Kickoff and discovery | 15% | Done |
| 2. Interviews and analysis | 25% | Done |
| 3a. Recommendations outline agreed with client | 10% | Done |
| 3b. Full draft recommendations | 20% | Started, not done |
| 4. Final report and workshop | 20% | Not started |
| 5. Implementation plan | 10% | Not started |
The week-6 data.
- Planned hours to date: 6 weeks × 40 = 240 hours, so 60% of the plan
- Completed milestones: 15% + 25% + 10% = 50% complete
- Approved timesheets: 260 hours logged. Two senior consultants did more of the interviews than planned, so the actual cost of those hours, at each person's own cost rate, is $27,300 (an average of $105 per hour)
Step 1: the three base values.
PV = 60% x $40,000 = $24,000
EV = 50% x $40,000 = $20,000
AC = $27,300 (from approved timesheets)Step 2: variances and indices.
CV = EV - AC = $20,000 - $27,300 = -$7,300
SV = EV - PV = $20,000 - $24,000 = -$4,000
CPI = EV / AC = $20,000 / $27,300 = 0.73
SPI = EV / PV = $20,000 / $24,000 = 0.83Step 3: forecasts.
EAC (typical) = BAC / CPI = $40,000 / 0.7326 = $54,600
ETC = EAC - AC = $54,600 - $27,300 = $27,300
VAC = BAC - EAC = $40,000 - $54,600 = -$14,600
TCPI (to hit BAC) = (BAC - EV) / (BAC - AC) = $20,000 / $12,700 = 1.57
EAC (atypical) = AC + (BAC - EV) = $27,300 + $20,000 = $47,300
EAC (CPI x SPI) = AC + (BAC - EV) / (0.7326 x 0.8333)
= $27,300 + $32,760 = $60,060(The EAC uses the unrounded CPI of 0.7326. Rounding to 0.73 first gives $54,795, which is why spreadsheets and reports often disagree by a few hundred dollars.)
Step 4: what it means in plain language.
- The project is 10 percentage points behind plan (50% done against 60% planned) and has spent 68% of its budget ($27,300 of $40,000) to finish half the work.
- For every $1.00 of cost, the team delivers $0.73 of planned work.
- If that efficiency continues, the project will cost about $54,600. Against a $56,000 fee, the margin falls from $16,000 to about $1,400, or 2.5%. If the team also crunches to recover the schedule (the CPI × SPI case), cost reaches about $60,060 and the project loses roughly $4,000.
- To come in on the original budget, the team would need a CPI of 1.57 on the remaining work. A team running at 0.73 does not suddenly run at 1.57, so the original budget is no longer a realistic target.
- In hours: at the actual average cost of $105, the $27,300 still to spend is about 260 more hours. The project is heading for roughly 520 hours against 400 planned.
That is the value of EVM. A plain budget report on week 6 would show "68% of budget used," which sounds like a project slightly ahead of pace. Earned value shows a project that is both late and over cost, early enough to act: renegotiate scope, move work to lower-cost staff, or raise a change request for the extra interviews.
How to read EVM results
CPI and SPI together
| SPI ≥ 1 (on or ahead of schedule) | SPI < 1 (behind schedule) | |
|---|---|---|
| CPI ≥ 1 (on or under budget) | Healthy. Check the estimate was not padded. | Cheap but slow. Often understaffed or blocked by the client. Add capacity if the deadline matters. |
| CPI < 1 (over budget) | Fast but expensive. Usually senior people or overtime buying speed. | The danger zone. Late and over cost, like the example above. Act this week. |
Set a tolerance, not a target of exactly 1.0
Small weekly swings are noise: one person logs Friday's hours on Monday, a milestone closes a day late. A practical rule is to set a band (for example 0.95 to 1.05) and act when an index stays outside it for two reporting periods in a row, rather than reacting to every wobble.
Do not expect the CPI to recover by itself
Christensen and Heise analyzed 155 US defense contracts and found that the cumulative CPI was stable from the 20 percent completion point, and that it tends only to get worse (Cost Performance Index Stability, National Contract Management Journal, 1993). Those were large defense programs, not 400-hour consulting jobs, and later researchers have questioned how far the finding generalizes. Still, the lesson holds for small projects too: a CPI of 0.73 at 50% complete is a forecast, not a blip. Treat BAC / CPI as the likely outcome, and justify any more optimistic EAC with a specific change you will make.
Watch the trend, not one snapshot
Plot CPI and SPI weekly. A CPI that falls from 0.95 to 0.88 to 0.81 over three weeks tells you more than any single value. A CPI that dips and recovers usually means timesheet timing, not real overruns.
How to measure earned value on time-and-materials and fixed-fee projects
EV is only as good as the percent complete you multiply by BAC. This is the step most guides skip, and the step that decides whether EVM works in a services firm.
Percent complete methods
The standard measurement techniques (sometimes called performance measurement techniques) are described in EVM tools such as Deltek Cobra. Here is how each one fits professional services work, applied to the week-6 example:
| Method | How EV is credited | Best for | EV in the example | CPI |
|---|---|---|---|---|
| 0/100 | Nothing until the task is done, then 100% | Short tasks that start and finish within one reporting week | 40% = $16,000 | 0.59 |
| 50/50 (or 25/75) | Half when the task starts, half when it ends | Tasks of two to four weeks | 55% = $22,000 | 0.81 |
| Weighted milestones | A fixed share of the budget for each milestone reached | Most consulting and engineering phases. Ties EV to deliverables the client sees | 50% = $20,000 | 0.73 |
| Units complete | Share of countable units done (drawings, pages, interviews, screens) | Repetitive deliverables, such as 40 drawings or 25 stakeholder interviews | Depends on the count | |
| Estimated percent complete | The task owner's judgment | Only when nothing objective exists. Ask for the hours left, not a percentage | Varies | |
| Level of effort (LOE) | EV equals PV for as long as the work goes on | Project management, account management, ongoing support | Always equals plan | |
| Hours spent / hours budgeted | Not an EV method | Nothing. This measures consumption | 65% = $26,000 | 0.95 |
The last row is the trap. If you treat "260 of 400 hours used" as 65% complete, EV rises in lockstep with spending and the CPI reads 0.95, a project that looks nearly on budget. The same project measured on milestones has a CPI of 0.73. The method you choose changes the answer, so pick one per task when you set the baseline and do not switch midway.
Two practical rules for small firms:
- Break work into tasks of one to three weeks and use 0/100 or 50/50 on them. You get objective EV with almost no admin.
- Keep LOE below a fifth or so of the budget. LOE always earns its plan, so a project that is mostly LOE will always report SPI = 1.0 and tell you nothing.
Fixed-fee projects
On fixed fee, earned value management matters most, because every overrun comes straight out of your margin.
- BAC = your internal cost budget (hours × cost rates), not the fee.
- EV = weighted milestones or 0/100 on tasks, tied to the deliverables in the contract.
- The number to watch: fee minus EAC is your forecast profit. In the example, that fell from $16,000 to $1,400 by week 6.
- If the client's billing plan follows the same milestones, EV also tells you when you can invoice. Unbilled earned value is work you have done and not yet been paid for.
Time-and-materials projects
On time-and-materials the client pays for every hour, so it is tempting to think EVM is irrelevant. It is not, for three reasons: most T&M work comes with an estimate or a not-to-exceed cap; the client judges you on whether the scope was delivered for roughly the estimate; and an overrun you cannot bill (because you hit the cap or the client pushes back) becomes a write-off.
- BAC = the estimate you gave the client, at cost or at bill rates. Pick one and use it for PV, EV and AC alike.
- EV = progress on the deliverables in the statement of work, never hours billed. Billable hours are AC in disguise.
- The number to watch: EAC against the cap. If EAC exceeds the cap at 30% complete, you have time to have the conversation before the invoice does it for you.
- When EVM does not fit: open-ended staff time with no defined deliverable. There is nothing to earn except effort, so EV equals AC by definition. Track burn rate against the cap instead.
Whichever contract type, connect EVM to your margin reporting. Our guide to project profitability tracking shows how the forecast feeds into project and firm-level margin.
Why timesheets are the source of actual cost
In a firm that sells time, labor is most of the cost, and the timesheet is the only record of who worked how long on which project and task. That makes the timesheet your AC, and the quality of your EVM depends on it.
What goes into AC:
AC = sum of (approved hours x that person's cost rate)
+ project expenses
+ subcontractor costsUse each person's cost rate (salary plus a share of overhead per billable hour), not their bill rate. If the budget was built at a blended $100 per hour but seniors cost $130 and juniors $75, only person-level cost rates show that a senior-heavy week burns the budget faster. If you do not know your loaded rates yet, the cost per billable hour calculator works them out from salary, overhead and utilization.
Timesheet habits that make EVM reliable:
- Daily entry, weekly approval. Time entered from memory on Friday drifts toward the plan. Approved weeks give an AC you can trust on Monday.
- Time on tasks, not just projects. If hours are logged against tasks, you can compare the cost of each milestone with its weight and see which part of the work overran.
- No missing time at the cut-off. Unsubmitted hours make AC look low and the CPI look healthy. Chase missing timesheets before you calculate, not after.
- Locked periods. If last month's hours can still change, last month's CPI can change too. Lock approved periods so reports stay put.
- A fixed cost per hour on each entry. If a raise in March recalculates January's cost, your historical CPI rewrites itself.
SUNAGO Matrix covers this part. The free timesheet gives every employee a timer, the Timesheet or just the total for the day, with approvals and locked periods, and it is free forever for every user. With Project management, time can be registered on tasks, and each task shows its estimate, the time spent and what is left. With Costs and rates, each time entry gets the cost price of the working day, which stays fixed afterwards unless an admin chooses Recalculate. With Project management and Costs and rates together, projects show budget, spend, forecast total cost and margin. See project cost tracking for the details. With Project management and Allocation and Resources, the project's Timeline can also show Ahead or behind: Schedule performance and Budget performance, week by week, where 1.00 is on plan and on budget. Matrix does not show EAC, ETC, VAC or TCPI under those names, but it gives you the clean actual cost and hour figures the formulas need.
Start with the free Timesheet and you will have the AC side of earned value from the first week.
Limitations of earned value management for small firms
EVM is a good tool, but it was built for large programs. ANSI/EIA-748, the standard behind EVM systems on US government contracts, has 32 guidelines, and the US Department of Defense requires compliance on cost or incentive contracts of $20 million or more (AcqNotes). A 10-person consultancy needs a small fraction of that. Know where it falls short:
- Percent complete is still partly judgment. Weighted milestones reduce the problem but do not remove it. Someone decided that "outline agreed" is worth 10%. Agree the weights with the team when you set the baseline, not when the numbers look bad.
- It needs a time-phased baseline. Without a plan of when the budget is spent, there is no PV and no SPI. Many small firms have a total budget but no weekly plan. A simple even spread or a phase-by-phase split is enough to start.
- Short projects give few data points. On a three-week project, by the time the CPI is meaningful the work is done. EVM pays off on projects of roughly six weeks and up, or several hundred hours.
- SPI always ends at 1.0. When the project finishes, EV equals PV equals BAC, so SPI returns to 1.0 even if you delivered a month late. Late in a project, SPI stops telling you anything. Earned schedule, which measures schedule performance in time units, fixes this and is included in PMI's current EVM standard.
- It measures cost and schedule, not quality or client happiness. A milestone marked done that the client then rejects earned value it did not deserve. Count a deliverable as done when the client accepts it.
- Scope changes break the baseline. If the client adds two workshops, update BAC and the milestone weights through a documented change, or every index after that point is wrong.
- It is only as good as the timesheets. Late, missing or unapproved time makes AC wrong, and every formula above inherits the error.
None of these are reasons to skip EVM. They are reasons to run a light version: milestones of one to three weeks, weekly calculation after timesheet approval, CPI, SPI and EAC on one line per project, and a conversation whenever an index stays outside your band.
A light EVM routine for a small firm
- At kickoff: set BAC at cost, split the work into weighted milestones or short tasks, and spread the hours over the weeks to get PV.
- Every Monday: approve last week's timesheets, mark milestones done, and calculate EV, AC, CPI, SPI and EAC.
- When an index stays outside your band for two weeks: find the cause (scope, staffing mix, client delays) and decide on one action.
- When EAC passes the fee or cap: talk to the client about scope or a change order before the overrun is spent.
- At closeout: compare final cost with the week-6 EAC. Over time that tells you how good your early forecasts are and how to price the next project.
Get the actual cost right first
Earned value management turns "68% of budget used" into "half done, $7,300 over cost and heading for a $54,600 finish." The formulas are simple. The hard part is reliable inputs: honest milestones for EV, and approved, task-level timesheets at real cost rates for AC.